Years ago,( at least a couple of decades) when I was an apprentice, my boss sent me to a job to drill out joist for a heating install.
I spent 2 1/2 days drilling through hardwood joists. I finished the drilling at lunch time on a friday and thought I would pack it it and go home.
I came back on monday with all the piping to find the electrician had used all my holes to feed his cables through over the weekend.
I went to see the Foreman, almost crying and explained the situation.
He asked me for a hacksaw and proceeded to remove the cables for me.
He also took great delight in informing the electrician of what had taken place, leaving out the part that he cut and removed the cables.
The days that followed were very interesting!
I spent 2 1/2 days drilling through hardwood joists. I finished the drilling at lunch time on a friday and thought I would pack it it and go home.
I came back on monday with all the piping to find the electrician had used all my holes to feed his cables through over the weekend.
I went to see the Foreman, almost crying and explained the situation.
He asked me for a hacksaw and proceeded to remove the cables for me.
He also took great delight in informing the electrician of what had taken place, leaving out the part that he cut and removed the cables.
The days that followed were very interesting!