cr0ft

Plumbers Arms member
Plumber
Gas Engineer
Messages
3,311
Hi all. Does anyone have a good reference with diagrams that explains how this works? Been asked to quote for a system which will require 2x 35KW System boilers and am wanting to install them both onto the same CH pipework. It will be a 3 zone system in a very large property.

Spoken with Viessmann and they have said the only special requirement is that they should be piped using a reverse return configuration. Can someone enlighten me? I have never installed more than one boiler in a property before.

Cheers!
 
Otherwise know as "first in - last out"

so if boiler one's flow is the first to connect to the pipe work then the return is the last.

Personally I would still use a low loss header even on a job like this.
 
Last edited:
I think they would have meant only a reverse return on the boilers on primary side, so it still includes a LLH
 
105631.gif
 
Status
Not open for further replies.

Reply to Reverse Return CH Piping in the Plumbing Jobs | The Job-board area at PlumbersForums.net

Similar plumbing topics

S
Hi, I seemed to have a blockage in kitchen sink. A plumber came and cleared all the pipework that is visible inside my home (there was debris and...
Replies
2
Views
161
Sonya K
S
We run a community village hall and have a large kitchen provided for the use of hirers. This includes a Lincat SLR9 gas cooker which I believe is...
Replies
5
Views
555
We are from Alberta, and I own an electrical company. I have been asked by a BC Mechanical P. Eng. to install an emergency STOP button at the...
Replies
5
Views
325
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock