15mm can do 2 rads k2 600 x 1400
 
Hi
How many time's can you tee off 15mm ch pipes that tee off 22mm from the combi boiler? Thanks

Hundreds of times, but depends on your flow rates :p
I normally say 15mm will take 5-6kW. What's the output of the circuits you're feeding?
 
If it's a combi I presume it's a sealed system.
Roughly speaking I always think up to around 20000- 25000 Btu's / hr.
There are other things to take into account though pipe runs, distance, temp, Delta T's etc.

That's why I think it is always best to get an experienced Heating Engineer in. If you try and take too much, you'll wish you hadn't.
 
Status
Not open for further replies.

Reply to Branching off pipe work in the Plumbing Jobs | The Job-board area at PlumbersForums.net

Newest Plumbing Threads

Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock