Hi guys,

I'm having some trouble with my builder and the plumber who fitted my underfloor heating. In a nutshell, the plumber has laid Hetta aluminium pipes over c. 40 square metres comprising of two zones. The builder has then laid around 6cm of semi dry aggregate-based fibre screed. He's then added self level compound on top. The only thing left to lay is karndean vinyl floor.

The problems I have identified to date are as follows :-

1. The water pipes were not hot when the screed was laid so I am worried that when they heat and expand, it will crack the screed. (I'm not sure whether this was the plumber or builders responsibility)

2. No insulation was applied around the edging of the screed so I guess there's a risk of cracking either within the screed or the wall plaster (again not sure if this was builder or plumbers responsibility)

3. The self level compound that's been applied was 10 bags of Palace compound mixed with 4 bottles of Febflor latex and 6 part water. (I'm not so worried about this given it's only about 2-3mm in depth).

particularly on the first point, it would be great to know what others recommend I do now? It's been about 3 weeks since the screed was laid so I believe it's too early for my to switch the heating on. I've got to make a call on whether I either :-

a) Crack on with laying the vinyl floor and fitting the kitchen and hope for the best

or

b) dig it all back out and do it again. This will cost c. £500 for the screed and another £1500 for the underfloor heating (presuming the pipes can't be saved).

Would welcome all opinions.

Thanks,

Steve
 

Attachments

  • 20200626_152101.jpg
    20200626_152101.jpg
    166.9 KB · Views: 27
  • 20200630_174120.jpg
    20200630_174120.jpg
    178.6 KB · Views: 27
Don’t need the heating on when you lay the screed but do need the pipes to be full of water and upto spec

this should be ok not the best or correct way but should be fine

normally 2L of water per bag but may differ consult manufacturers instructions
 
Definitely no heat on whilst screeding. But should have been pressure tested to manufacturers requirement then left at a couple of bar whilst screeding. Slight pressure increase as the concrete goes in and heats up.
Plumbers issue, but builder would have had to let him know when he was screeding.

Edging insulation more to stop heat bleeding into the building structure.

Personally I would warm the floor very gradually in line with the requirements of the screed prior to laying the vinyl flooring. Also the same with the self leveller but that's just me. But I would be annoyed at the new screed needing a self levelling compound.
 
As said above, it isn't the ideal install but should be OK. My only other concern would be normally there is a foam edging strip placed around the perimeter of the room to absorb the expansion of the screed slab when it is hot, I believe it helps avoid cracking. Not sure how vital it is, may be worth asking a UFH company and see what they say.
 
As above not ideal the slab will expand and contract and it really should have perimeter insulation , pipework should of been pressure tested and left pressured up whilst screeding , I would warm the slab if possible over a week if you have floor stats this will be simple to do starting a couple of degree increase each day a long slow warming is better than a thermal shock which could possibly cause cracking , I wouldn't be laying any floor coverings until you're confident the floor is sound and the Ufh hold pressure. Kop
 
The edge strip is to reduce thermal bridging and also allow a modest amount of expansion for the screed. If you are paying £1500 for 35m2 you are being well ripped off! You need to bring the UFH slowly upto temperature or you will thermally shock the new screed resulting is a cracked / damaged floor.
 
Thanks for the all the replies. After the screed, he's now done two very thin rounds of self level compound in order to get it level. Not ideal at all but I've got to crack on with the job in order to move into the house. Fingers crossed it all works out!

@StephenF - That's interesting that you think I got ripped off. I did get 3 or 4 quotes for the job and all came in at either the same price or higher. What would you expect that kind of size room to cost? (Noted on slowly increasing the temp, I'm not even thinking about switching the heating in for another month or so yet and then will do so in small increments daily)
 
Op are you sure about the competence of the people on this job?

the cable running to the outlet below and to the left of the boiler isn’t in safe zones and isn’t acceptable, and needs improvement before you plaster
 

Reply to Underfloor heating worries in the USA area at PlumbersForums.net

Similar plumbing topics

Hi, Can anyone advise as to why the cold water to my bathroom keeps airlocking? This originally happened about 12 months ago and has happened 3-4 times since. It’s an upstairs bathroom, fed from a tank in the attic. The tank is about 8 Meters away and feeds a bath, sink and toilet. The tank...
Replies
9
Views
241
Our kitchen mixer tap has started dripping. Like so much of the plumbing in our almost new build bungalow, it is lacking! The plumber didn't install any isolating cocks in the H&C feed to the tap so how can I identify which of the valves is passing? Shut the whole H&C water system down?
Replies
7
Views
157
Hi all I'm hoping someone can shine a light on this for me Since our stop tap on the pavement has now been filled with sand for whatever reason, we are relying on our property fitted stopcock (this is outside on our garage wall) Unfortunately turning this to the closed position only reduces...
Replies
2
Views
141
I want to reconnect some outbuildings to an existing water supply. The supply pipe is old 22mm MDPE and buried for a fair distance so not going to dig it up and replace it 😬. Question is can I use normal 22mm plumbing push-fit connectors to make the connection as finding 22mm MDPE fittings...
Replies
1
Views
179
Copper pipes, I think its fair to say, is not what it used to be, the copper is getting thin while the cost is going up. Meanwhile, plastic Pushfit seems to be getting better and better, cost and convenience was always better, but now the quality is to, have we reached a stage where plastic will...
Replies
2
Views
158
Creating content since 2001. Untold Media.

Newest Plumbing Threads

Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock