Im after some advice please. This is a bit difficult to explain so i have added some pics.
I am adding an ensuite to the house. As part of this i am adding a new soil stack as the original soil stack is at the back of the property and ensuite is at the front.
My problem is i need to route this stack/line into the existing manhole. I am adding and IC where there is a change in direction. The direction this new line enters the manhole is opposite to the direction the manhole currently flows.
I was thinking of breaking into the manhole and then benching a substantial enough bend to direct towards the outlet flow.
Can anyone advise if this is ok or if there is a better solution. I do not want to in anyway alter the existing clay pipes which i think are 6 inch.
I have added a bend straight over the outlet (not blocking it) - this is just a dry run for illustation - do you think this is ok or does it need to come in and benched into a bend towards the flow.
I have building control involved who i can call out at some point but im just wondering the options
Im after some advice please. This is a bit difficult to explain so i have added some pics.
I am adding an ensuite to the house. As part of this i am adding a new soil stack as the original soil stack is at the back of the property and ensuite is at the front.
My problem is i need to route this stack/line into the existing manhole. I am adding and IC where there is a change in direction. The direction this new line enters the manhole is opposite to the direction the manhole currently flows.
I was thinking of breaking into the manhole and then benching a substantial enough bend to direct towards the outlet flow.
Can anyone advise if this is ok or if there is a better solution. I do not want to in anyway alter the existing clay pipes which i think are 6 inch.
I have added a bend straight over the outlet (not blocking it) - this is just a dry run for illustation - do you think this is ok or does it need to come in and benched into a bend towards the flow.
I have building control involved who i can call out at some point but im just wondering the options
Attachments
-
1a323b5b-76a8-4dfe-8214-6e5b6e417bc0.jpg200.6 KB · Views: 45
-
1d4f0326-ea35-4416-8eb6-027a971f1b7b.jpg205.4 KB · Views: 41
-
a76bc25d-ed51-4614-801d-fab0c12c087a.jpg197.9 KB · Views: 40
-
61f87833-ff30-4cbe-bd74-8870dc0a1250.jpg150.3 KB · Views: 39
-
aa095d16-980f-4f0e-befb-af9c92d197dc.jpg210.6 KB · Views: 40