The boiler is installed, it just needs commissioning, I suppose when there are no faults because if there are then it is the same as asking how long is a piece of string?

The boiler is an Ideal Logic Max c35Kw, if that makes any difference.

Cheers
 
give us a bit more ! , why didnt the installer commission it ?
Sure - I posed the question badly....
What I meant is how long does it take to undertake the Benchmark Commissioning Checklist? If that is a daft question, them my apologies.

I want to know because the boss called me at 16:15 and said that the boiler would be up and running later that same day, but looking at thephotos, it seems that there was still quite a lot of work to do, including the commissioning. Safe to say, that the job ran over.

Actually, I can upload some photos, the first is what it looked like at 17:51 on the day of the install (some way off a finished job) and the remaining ones are what it looked like post commissioning on-hand over to the customer, bar the last one is what it looked like once they had returned and sealed the internal seal.- - following an AT RISK notice issued by the manufacturer.

And yes, the original flue terminal exit, was left open and exposed to the elements (it was the 24-25th January).
 

Attachments

  • 007 Flue Installation In-Progress.jpg
    007 Flue Installation In-Progress.jpg
    157.8 KB · Views: 26
  • 1-Hometeam Installation of Flue taken 2019 06 15 (7).jpg
    1-Hometeam Installation of Flue taken 2019 06 15 (7).jpg
    178.9 KB · Views: 26
  • 1-IMG_20220427_170034.jpg
    1-IMG_20220427_170034.jpg
    218.3 KB · Views: 23
  • Hometeam Installation of Flue taken 2019 06 15 (2).jpg
    Hometeam Installation of Flue taken 2019 06 15 (2).jpg
    185.2 KB · Views: 23
  • IMG_20220427_170011.jpg
    IMG_20220427_170011.jpg
    266.8 KB · Views: 25
  • 1-IMG_20220427_170533.jpg
    1-IMG_20220427_170533.jpg
    217.2 KB · Views: 26
I normally allow for an afternoon for completing / filling in the paperwork , commissioning and filling / making good
 
They should make good the old flue hole, at least temporarily block it up until they can.

Didn't you say this was a listed building? I must say all that flue hanging in a residential won't and doesn't look great.
 

Reply to How long does it take to Commission a new boiler in the Gas Engineers Forum area at PlumbersForums.net

Similar plumbing topics

Hi guys. I'm trying to identify a toilet model before ordering a seat for a customer. I went to what used to be a Roca stockist (they no longer are) and one of the guys there reckoned it might be "The Gap". I went to the new stockist and the guy there disagreed it was "The Gap" and that he'd...
Replies
2
Views
124
  • Sticky
Morning to any Australians lurking around! Register its free, then message me, I'll sort your account out for you. We will need a moderator from each main country too. I'll post this in the Australian forum now.
Replies
0
Views
65
Creating content since 2001. Untold Media.

Newest Plumbing Threads

Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock