I have a job coming up in a house where the primary F&E is in the loft and has a tap pouring into the top of it (!) and also a combined feed and vent in 15mm. Am planning to fit FOV, add a 22mm vent, and an overflow.

My concern is that the combined cold water storage and indirect-cylinder feed cistern is on the ground floor and therefore at a lower height (pressure) than the primary cistern.

I have advised the customer that it would be a good idea to move the latter cistern into the loft to prevent contamination of the stored water in the event of cylinder coil failure. Customer likes idea and keen to get better water pressure, but reluctant to have upheaval at present - wants to rent house out.

I can't find anything in the Water Regulations that specifically says that the water level in the F&E should be higher than that in the Cold Water Storage (and cylinder feed) Cistern, but may be I'm not looking in the right place. I've said I'll do just the F&E... reluctantly - IF there isn't a regulation on this.

Is having the F&E water level lower a regulation, or just good practice? Many thanks if anyone can help!

R
 
Hi Ric
This may be a little late but as far as I am aware there is nothing that states that the F&E cistern water level must be below that of the secondary feed cistern. It is a recommendation just incase as you say the coil splits.

If you think about it we still have Primatic cylinders out there & pressurised heating systems with open vented hot & cold, so the potential for primary water to enter is still there but it would be cause of a failure which is a rare event.

I would certainly go with the auto fill (FOV) if it is going to be let & min size for combi feed & vent is 22mm but can't you leave the 15mm as cold feed & run the new 22mm as SOV pipe ?
 
Hi Chris,

My concern was that pressurised systems only leak a bit before they lose pressure and people have to top up pressure - at least this gives some warning, but thanks, as you say, I'll take on the job.

I'll be leaving the old 15mm combined feed and vent (if it isn't blocked) as the new feed (this was already contrary to the MI from when the boiler was fitted in the late 80s), and add a 22mm as an open vent, as you say.

Apparently the primary pipework occasionally starts banging from the boiler. I suspect the boiler is kettling slightly and the pipework is not laid to a slight rise all the way to the vent and that this is causing problems. Unfortunately the pipework is boxed in, but the customer is happy to proceed on the basis that there is some additional investigation work required, so all should be well.

Thanks again.

Ric
 
Status
Not open for further replies.

Reply to Comparative heights of primary and cold water storage cisterns in the Plumbing Jobs | The Job-board area at PlumbersForums.net

Similar plumbing topics

Hi, I wonder if you could help me. The overflow pipe drips intermittently from the large cold water storage tank in the loft. Not the small F and E tank. The ball valve has been checked and is working ok. The vent pipe from the hot water cylinder is not venting any water into the tank, and the...
Replies
4
Views
914
I live in an apartment block where generally hot water is supplied from the communal hot water cylinder and cold water to bathrooms is supplied from cold water tanks in the loft. It is a vented system. However, in a basement flat and a ground floor flat cold water supply to bathrooms is...
Replies
4
Views
572
Hello, I have just installed a vented McDonald 250L thermal store, it is for multi fuel but currently just connected to a standard oil boiler in the garage which is fully pumped to the TS, the system has two pumps both basic 3speed Grunfoss, one on the boiler return and the other on the CH flow...
Replies
22
Views
1K
    • Like
Hi I recently did some pipe insulating in my loft. The only two I didn't do were the vent pipes. Not sure if that is the right term for them? They are the pipes that feed water back into the top of the tanks when there is excess, presumably from steam, expansion, etc. The one going to the cold...
Replies
2
Views
330
I recently installed new hot and cold feeds to a new downstairs cloakroom. After refilling the system the hot taps were all dribbling, spluttering and showing signs of an air lock. I attached cold mains to a hot tap and left it running for 15 minutes, while opening up each hot tap. They all...
Replies
2
Views
500
Creating content since 2001. Untold Media.

Newest Plumbing Threads

Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock