Since July I've been self-building a 500sqft cabin which has been a perfect way to keep busy and away from others. It has been an incredible learning experience and so rewarding to work with my hands (I am stuck on a computer all day for my day job so this is a welcome change). I got things weathered in before snow, and am now working on adding the utilities over the winter months. I really enjoy learning and doing these things myself, but am outsourcing the electrical and propane hookups for insurance reasons.

The plumbing I would like to do myself and have been reading up on what I need and pieced together knowledge from the National Plumbing Code of Canada, various books, websites, and this forum which have all helped me get a basic understanding of how to rough in my drain, waste, and vent piping.

I'm hoping to get some feedback on the design I came up with and understand 2 main things:
1) Is there anything here that is WRONG?
2) Is there anything I can do to make this more efficient without sacrificing function?

The cabin is on a pier and beam foundation and I have pretty good access underneath. The kitchen and bathroom are back to back so all the plumbing is concentrated within a small area. There's a loft above and I'm trying to avoid putting plumbing in the exterior walls where possible. We're also pretty remote so we'll be using solar on the south roof so I am trying to keep the stack vent in the corner so it's out of the way as much as possible.

Pic 1 is the floor plan to show where the fixtures and non-load-bearing 2x4 wall is located
Decluttered-floor-plan-for-plumbing.png

The small closet beside the stacked washer/dryer will serve as a utility closet housing the HRV/ERV, tankless propane hot water heater, well control box, pressure tank, and hopefully have a little bit of room left for some storage.

Pic 2 is a SketchUp drawing of the DWV rough in that I came up with. I am not the best with this software so I can't figure out how to change the piping sizes without starting from scratch but the toilet arm and waste pipe below the floor would all be 3" as well as the main stack vent up thru the roof.
DWV-SketchUp-1.jpg

I put the vents up thru the loft floor joists since I am able to bore holes of sufficient diameter in those 2x12s for the horizontal connections, but not in the 2x6 exterior wall studs. The kitchen piping I have kept just outside of the wall and the trap arm will end up behind base cabinets and the stack portion would be in the utility closet.

Pic 3 is another SketchUp view from below.
DWV-SketchUp-2.jpg


There is also a 4ply beam below the floor joists which prevents me from going straight down thru the sill. I couldn't figure out how to sketch this with a 45 degree bend so there are 2 90s instead. I was intending to do a 45 from below the sill to use less fittings and smooth things out.

So, am I on the right track here? Anything wrong? Anything I can improve?

Thanks in advance for any feedback!
 

Reply to Cabin DWV Rough In - Am I on the Right Track? in the USA area at PlumbersForums.net

Similar plumbing topics

60's ranch, with single bathroom. Tile over concrete slab. Toilet is about a foot from exterior brick wall. Vent pipe is in interior wall behind toilet. There's a concrete patio outside the bathroom, that extends about 10 feet from the wall. I'm considering adding an ADU in the back yard, and it...
Replies
1
Views
176
Hi guys not sure anyone has encountered this before but I have a job where the inside wall has been getting a little damp, there was a step up to the door that I think wasn't helping due to dpc but that was removed to take a closer look and it revealed 2 waste water pipes going into the patio...
Replies
1
Views
371
Hi all, Would welcome your thoughts on this. I'm installing a low level shower tray, over a timber floor. Cast iron soil stack only about a metre away. So far so good. The problem is that the existing 1 1/2 copper connection into the stack (previously serving bath) enters the stack at a low...
Replies
11
Views
1K
Hi All, I'm due to start building a new side extension on a 3 bed semi, it's across the driveway up to the boundary. We're adding a downstairs toilet and utility room. The existing soil stack will be retained and boxed in with added rodding eye as it's well positioned for the existing 1st...
Replies
8
Views
925
Hi guys, first post here So I have been boxing in a number of heating pipes that are throughout my garage since the boiler was located there by the previous owner, they decided to run pipes all along the edge of the garage floor... I do however have one that goes vertically out of the concrete...
Replies
1
Views
196
Creating content since 2001. Untold Media.

Newest Plumbing Threads

Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock